Question 1
Single answer
What is the end purpose of introducing a Total Quality Management process to the operations department of an organisation?
Show answer
Correct answer
-
A
customer satisfaction
Explanation
Total Quality Management places customer-defined quality at the centre of management decisions. Customer needs inform design, purchasing, production, service delivery and the treatment of complaints. Managers must monitor satisfaction as well as internal defect rates, because technically compliant output can still disappoint buyers. Lower costs, fewer defects and greater market share are possible consequences of delivering consistent value; they are not substitutes for understanding and satisfying customers. A successful quality programme coordinates design, suppliers, operations and customer feedback. Preventing defects generally provides greater value than discovering them after production, although verification remains essential. Improvement must therefore link preventive controls, capable employees and meaningful measures of customer-defined quality. The appropriate selection is customer satisfaction. This follows from the distinction between the concept described and the alternative activities or measures in the answer choices. Management commitment and employee competence are necessary to translate the quality approach into stable everyday operating practices. The wider management implication is to define the requirement precisely, monitor the relevant outcome and act on deviations before they become established operating problems.
Study Guide CIPS L5M9 – Evaluate the role of total quality management in operations management; the uploaded question bank cites study-guide page(s) 105.
No comments yet. Start the discussion.
-
A
-
Question 2
Multiple answer
How can a company measure the dependability of an item it produces? Select TWO
Show answer
Correct answer
-
A
number of injuries caused by the product
-
E
documentation is accurate
Explanation
Dependability encompasses reliable functioning over time, availability and, in safety-related applications, freedom from unacceptable harm. Injury counts can indicate safety problems, while accurate product instructions help users operate and maintain goods properly. Neither indicator alone quantifies reliability: a sound assessment also examines failure rates, mean time between failures and warranty returns. Complaint response time measures service speed; choice of colours relates to flexibility; gross margin is financial. Effective application requires a clear baseline and a mechanism for testing whether action improved performance. Managers should distinguish leading indicators from final outcomes and avoid drawing causal conclusions from simple association. The strongest tools connect evidence, decisions and sustained operational controls. The required selections are number of injuries caused by the product and documentation is accurate. These choices address the particular category named in the question, whereas the remaining alternatives describe other activities, dimensions or outcomes. Consistent measurement and periodic review are necessary to distinguish a sustained improvement from a temporary or misleading change.
Study Guide CIPS L5M9 – Analyse tools for improving performance in operations management; the uploaded question bank cites study-guide page(s) 76.
No comments yet. Start the discussion.
-
A
-
Question 3
Single answer
Terrance is an Operations Director at a pharmaceutical company which produces vaccines. He has been made aware of a malfunctioning piece of equipment with a Mean Time between Failures rating of 2 days. What characteristic of the machinery is being measured?
Show answer
Correct answer
-
B
reliability
Explanation
Mean Time Between Failures measures average operational time between failures of repairable assets. It is a reliability metric rather than a cost or durability measure. If machinery runs for 240 hours and fails five times, the observed MTBF is 48 hours, or two days of continuous operation. This is an average, not a prediction that failure will occur precisely every second day. Availability additionally depends on how quickly the machine is restored after a failure. Where consequences are significant, managers should prioritise preventive controls, reliable monitoring and prompt restoration. Performance measures such as downtime, MTBF, repair time and availability help identify weaknesses. The chosen technique must also account for costs, safety and the possibility of common-cause failures. The appropriate selection is reliability. This follows from the distinction between the concept described and the alternative activities or measures in the answer choices. Documented responsibilities, suitable spare capacity and tested recovery arrangements can reduce the duration and consequences of disruption.
Study Guide CIPS L5M9 – Explain techniques in failure prevention and recovery that can be applied in operations management; the uploaded question bank cites study-guide page(s) 94.
No comments yet. Start the discussion.
-
B
-
Question 4
Single answer
At which point in the manufacturing process would Failure Mode and Effects Analysis (FMEA) be first used?
Show answer
Correct answer
-
A
before manufacturing begins
Explanation
Failure Mode and Effects Analysis is most valuable while product and process decisions remain open to change. Design FMEA examines design weaknesses; Process FMEA examines potential manufacturing mistakes and control failures. Analysts identify failure modes, effects, causes and safeguards, then prioritise actions using severity, occurrence and detection or a modern action-priority scheme. FMEA should be updated after process modifications and field failures, but its preventive value is highest before mass production commits resources to an unsuitable design. Reliable operations depend on designing out avoidable faults and responding systematically when failures occur. Teams should capture defect and incident evidence, identify root causes and test corrective actions. A response that merely restores service without addressing repeat failure may increase long-term operating costs. The appropriate selection is before manufacturing begins. This follows from the distinction between the concept described and the alternative activities or measures in the answer choices. Documented responsibilities, suitable spare capacity and tested recovery arrangements can reduce the duration and consequences of disruption.
Study Guide CIPS L5M9 – Explain techniques in failure prevention and recovery that can be applied in operations management; the uploaded question bank cites study-guide page(s) 97.
No comments yet. Start the discussion.
-
A
-
Question 5
Multiple answer
When conducting Failure Mode and Effects Analysis (FMEA), which systems could be used to communicate or assess risks to business operations? Select TWO.
Show answer
Correct answer
-
C
Red-Amber-Green (RAG) system
-
D
A numerical scale from 1 to 10
Explanation
Traditional FMEA can score severity, occurrence and detection on numerical scales, often from one to ten, and combine these into a risk priority number. A red–amber–green summary may be used internally to communicate priorities to managers, provided thresholds are defined and do not displace analysis of severe risks. ABC analysis is primarily an inventory classification technique. Generic colour coding overlaps with RAG but does not itself specify a consistent risk-assessment method. A comprehensive failure-prevention programme considers the probability of failure, the consequences of interruption and the effectiveness of detection and recovery arrangements. Controls should be proportionate to asset criticality and reviewed using failure records, maintenance information and operational experience. The required selections are red-amber-green (rag) system and a numerical scale from 1 to 10. These choices address the particular category named in the question, whereas the remaining alternatives describe other activities, dimensions or outcomes. Documented responsibilities, suitable spare capacity and tested recovery arrangements can reduce the duration and consequences of disruption.
Study Guide CIPS L5M9 – Explain techniques in failure prevention and recovery that can be applied in operations management; the uploaded question bank cites study-guide page(s) 99.
No comments yet. Start the discussion.
-
C
- Unlock to see this question
- Unlock to see this question
115 questions locked
Unlock all 120 L5M9 questions
You’ve had 5 for free. The other 115 work just like them: pick an answer, then check it.
- Questions
- 120, each with its answer
- Explanations