CTAL-AT Practice questions
ISTQB Certified Tester Advanced Level - Agile Tester (CTAL-AT)
0/10 checked
- free questions
- 10
- with answers
- in the full set
- 520
- question types
- 2
Updated
-
Question 1
Single answer
A team's product owner revises requirements every few days. New user stories arrive with a one-line description and a single acceptance criterion, and the iteration leaves the tester about half a day per story for test analysis and design. A new story for bulk-editing customer tags has just been delivered for testing.
Which test approach should the tester apply to this story?
Select ONE answer.
Show answer
Correct answer
-
C
Charter-based exploratory sessions that adapt as the story changes
No comments yet. Start the discussion.
-
C
-
Question 2
Single answer
For a new feature, a team needs tooling to create and run its unit tests, its API tests, its GUI tests and a set of manual test cases.
Which statement BEST describes the tool category that covers this need?
Select ONE answer.
Show answer
Correct answer
-
B
Test design, implementation and execution tools, which support automated and manual tests
No comments yet. Start the discussion.
-
B
-
Question 3
Single answer
A team is building a booking web application for a network of community sports centers. Builds are assembled by hand by a separate operations group, as the organization has no CI/CD pipeline. The team has no test doubles or service virtualization, and containers are not permitted on the shared servers. Releases go out monthly, and the domain carries no special legal or safety obligations.
The test manager is outlining the project test strategy. Which strategy element BEST fits these tooling constraints?
Select ONE answer.
Show answer
Correct answer
-
A
Mainly manual Quadrant 3 testing, offset by broader exploratory coverage and feature toggles
No comments yet. Start the discussion.
-
A
-
Question 4
Single answer
A developer says a user story is finished because its code has been merged, but the increment still fails the performance and accessibility checks that the product requires. The team points to its Definition of Done.
Which explanation of what the Definition of Done describes is MOST accurate?
Select ONE answer.
Show answer
Correct answer
-
C
It formally describes the state of the increment when it meets the quality measures required for the product
No comments yet. Start the discussion.
-
C
-
Question 5
Single answer
A tester is chartering a session for the user story 'As a team lead, I want to rate each backlog item's quality risk as low, medium or high so that testing effort can follow the risk.' The charter's Activities field already lists three ideas: rate a new backlog item, change an existing rating, and view the backlog sorted by risk rating.
Which entry BEST belongs in the charter's Variations field?
Select ONE answer.
Show answer
Correct answer
-
D
Change a rating while another lead edits it; undo a rating change
No comments yet. Start the discussion.
-
D
-
Question 6
Single answer
A team writes its acceptance criteria in Given/When/Then form and automates them as executable specifications.
Which description of how bias can affect these artifacts is MOST accurate?
Select ONE answer.
Show answer
Correct answer
-
A
Tests built on biased criteria grow ambiguous, because bias reduces the criteria's clarity
No comments yet. Start the discussion.
-
A
-
Question 7
Single answer
A pair has tested together for several sessions, and the same person has driven every time while the other has always navigated.
Which change BEST addresses the risk in this pattern?
Select ONE answer.
Show answer
Correct answer
-
D
Clearly define driver and navigator, then switch them regularly
No comments yet. Start the discussion.
-
D
-
Question 8
Multiple answer
An Agile team wants to agree which events should prompt it to adjust its testing during an iteration.
Which TWO inputs should the team treat as critical triggers for test control decisions?
Select TWO answers.
Show answer
Correct answer
-
C
A rise in failing automated regression checks after a merge
-
E
Production monitoring alerts showing rising error rates in a feature released last week
No comments yet. Start the discussion.
-
C
-
Question 9
Single answer
A team finds pair testing valuable but is concerned about the effort it consumes when two people work on every task.
Which approach BEST addresses this concern?
Select ONE answer.
Show answer
Correct answer
-
B
Pair strategically on complex or high-risk features only, to contain the effort
No comments yet. Start the discussion.
-
B
-
Question 10
Single answer
Two teams document the same feature. Team A writes "The report should load fast and look professional." Team B writes "The monthly report lists every account with its closing balance, sorted by account number."
Which statement BEST explains why Team B's specification supports shift left?
Select ONE answer.
Show answer
Correct answer
-
A
Its precise wording guides early test creation, so anomalies are found sooner
No comments yet. Start the discussion.
-
A
- Unlock to see this question
- Unlock to see this question
510 questions locked
Unlock all 520 CTAL-AT questions
You’ve had 10 for free. The other 510 work just like them: pick an answer, then check it.
- Questions
- 520, each with its answer
- Formats
- Single answer, Multiple answer
- Version
- 6.0
- Access
- 3 months from purchase
One-time payment
$149.00
Secure checkout